Exams

Study Notes
  • Regulatory
  • Teaching Exams
Mock Tests
  • Banking & Insurance
  • SSC Exams
  • Regulatory
  • UPSC
  • MBA Exams
  • Railway Exams
  • JAIIB-CAIIB Exams
  • Karnataka Exams
  • Tamil Nadu Exams
  • Judiciary Exams
  • Law Entrance Exams
  • Agriculture Exams
  • J&K Exams
  • UP Exams
  • Rajasthan Exams
  • Uttarakhand Exams
  • Punjab Exams
  • Haryana Exams
  • MP Exams
  • Defence Exams
  • Teaching Exams
  • Chhattisgarh Exams
Previous Year Papers
  • Banking
  • SSC
  • Regulatory
  • JAIIB
  • Teaching
  • Railways
Category
  • Banking & Insurance
  • SSC Exams
  • Regulatory
  • UPSC
  • MBA Exams
  • Railway Exams
  • JAIIB-CAIIB Exams
  • Karnataka Exams
  • Tamil Nadu Exams
  • Judiciary Exams
  • Law Entrance Exams
  • Agriculture Exams
  • Engineering Exams
  • J&K Exams
  • UP Exams
  • Rajasthan Exams
  • Uttarakhand Exams
  • Punjab Exams
  • Haryana Exams
  • Bihar Exams
  • MP Exams
  • Defence Exams
  • Teaching Exams
  • Himachal Pradesh Exams
  • Chhattisgarh Exams
  • SkillVertex Courses
Chhattisgarh Exams
Engineering Exams
Teaching Exams
Himachal Pradesh Exams
Chhattisgarh Exams

Previous Year Questions

Get Detailed Solutions for Previous Year Questions for Bank, SSC, Railways and Other Popular Government Exams

Question :

Following question consists of three statements numbered I, II and III given below it. You have to decide whether the data provided in the statements are sufficient to answer the question. Read all the three statements and give answer:

Three persons A, B and C together can finish a work in 10 days when A is working with 50% of his efficiency, B is working with 15/8th of his efficiency and C is working with 60% of his efficiency. Find the time taken by all of them to finish the work when working with their original efficiencies.

Statement I: Ratio of original efficiency of A to B is 3: 4.

Statement II: Time taken by B and C together to finish the work when working with their original efficiency is 40/3 days.

Statement III: Time taken by A alone to finish the work is 16 days more than the time taken by C alone to finish when working with their original efficiencies.

1. Statements I alone is sufficient.

2. Statement III alone is sufficient.

3. Statements I, II and III together are not sufficient.

4. Any two of statements I, II and III together are sufficient.

5. Statements II alone is sufficient.

Correct Answer : 4
Solution :

Let time taken by A, B, and C alone to finish the work working with their original efficiencies is 'a' days, '15b' days, and '3c' days respectively.

Time taken by A alone when working with 50% of original efficiency = a * (100/50) = 2a days

Time taken by B alone when working with 15/8th of original efficiency = 15b * (8/15) = 8b days

Time taken by C alone when working with 60% of original efficiency = 3c * (100/60) = 5c days

According to the question:

(1/2a) + (1/8b) + (1/5c) = (1/10) ........ (1)

From I:

Ratio of original efficiency of A to B = 3: 4

Ratio of time taken by A and B = 4: 3 = a: 15b

a = 20b ......... (2)

Statement I alone is not sufficient.

From II:

(1/15b) + (1/3c) = (3/40) ......... (3)

Statement II alone is not sufficient.

From III:

a - 3c = 16 ....... (4)

Statement III alone is not sufficient.

From I and II:

From equations (1), (2) and (3):

(1/40b) + (1/8b) + (1/5c) = (1/10)

(3/20b) + (1/5c) = (1/10)

(1/15b) + (1/3c) = (3/40)

b = 2, c = 8 and a = 40

Time taken by all of them to finish the work when working with their original efficiencies = 1/[(40) + (1/30) + (1/24)] = 120/(3 + 4 + 5) = 10 days

Statements I and II together are sufficient.

From I and III:

From equations (1), (2) and (4):

(1/40b) + (1/8b) + (1/5c) = (1/10)

(3/20b) + (1/5c) = (1/10)

a - 3c = 16

20b - 3c = 16

b = 2, c = 8 and a = 40

Time taken by all of them to finish the work when working with their original efficiencies = 1/[(40) + (1/30) + (1/24)] = 120/(3 + 4 + 5) = 10 days

Statements I and III together are sufficient.

From II and III:

From equations (1), (3) and (4):

(1/2a) + (1/8b) + (1/5c) = (1/10)

(1/15b) + (1/3c) = (3/40)

a - 3c = 16

b = 2, c = 8 and a = 40

Time taken by all of them to finish the work when working with their original efficiencies = 1/[(40) + (1/30) + (1/24)] = 120/(3 + 4 + 5) = 10 days

Statements II and III together are sufficient.

So, any two of statements I, II and III together are sufficient.

RBI Grade B Previous Year Papers

Attempt RBI Grade B Phase 1 PYPs, get detailed solutions

RBI Grade B Phase 1 Mock Test

Attempt RBI Grade B Phase 1 Mocks in Latest Pattern

Create a free Oliveboard account to access all PYQs with solutions & video explanations

RBI Phase I PYP Test Series

RBI Grade B Phase 1 PYP 2024 - 8th September Shift 1

200 200 2 Hours
Free

RBI Grade B Phase 1 PYP 2024 - 8th September Shift 2

200 200 2 Hours

RBI Grade B Phase 1 PYP 2023 - 9th July Shift 1

200 200 2 Hours

RBI Grade B Phase 1 PYP 2023 - 9th July Shift 2

200 200 2 Hours

RBI Grade B Phase 1 PYP 2022 - 28th May Shift 1

200 200 2 Hours

RBI Grade B Phase 1 PYP 2022 - 28th May Shift 2

200 200 2 Hours

RBI Grade B Phase 1 PYP - 6th March Shift 1

200 200 2 Hours

RBI Grade B Phase 1 PYP - 6th March Shift 2

200 200 2 Hours

RBI Grade B Phase 1 PYP 2019 - 9th November Shift 1

200 200 2 Hours

RBI 2025 Phase I Test Series

RBI 2025 Phase I - 1

200 200 2 Hours
Free

RBI 2025 Phase I - 2

200 200 2 Hours

RBI 2025 Phase I - 3

200 200 2 Hours

RBI 2025 Phase I - 4

200 200 2 Hours

RBI 2025 Phase I - 5

200 200 2 Hours

RBI 2025 Phase I - 6

200 200 2 Hours

RBI 2025 Phase I - 7

200 200 2 Hours

RBI 2025 Phase I - 8

200 200 2 Hours

RBI 2025 Phase I - 9

200 200 2 Hours

RBI 2025 Phase I - 10

200 200 2 Hours

RBI 2025 Phase I - 11

200 200 2 Hours

RBI 2025 Phase I - 12

200 200 2 Hours

RBI 2025 Phase I - 13

200 200 2 Hours

RBI 2025 Phase I - 14

200 200 2 Hours

RBI 2025 Phase I - 15

200 200 2 Hours

RBI 2025 Phase I - 16

200 200 2 Hours

RBI 2025 Phase I - 17

200 200 2 Hours

RBI 2025 Phase I - 18

200 200 2 Hours

RBI 2025 Phase I - 19

200 200 2 Hours

Record Breaking Results in 2024-25 🎉

Niranjan Jain

Niranjan Jain

Rank #1

SBI PO

â–¶
Amit Mandal

Amit Mandal

Rank #1

IBPS PO

â–¶
S B Tanay Gaurav

S B Tanay Gaurav

Rank #1

RBI Gr. B

â–¶
Shubham Agrawal

Shubham Agrawal

Rank #1

SSC CGL

â–¶
Manjot Singh

Manjot Singh

Rank #1

SSC CGL (JSO)

â–¶
Rohit Chadhar

Rohit Chadhar

Rank #1

SSC CHSL

â–¶
Shekhar Kumar

Shekhar Kumar

Rank #8

RBI Gr. B

â–¶

Please wait...

Open in app